jordan pulse -
An official report revealed a delay in the completion of one of the projects of the National Center for Diabetes and Endocrinology, which led to the loss of the benefit of providing the University of Jordan Fund and the Diabetes Center with financial revenues.
This delay occurred in Bid No. (A.M./10/2018), as it became clear when the field inspection was conducted by the Bureau’s engineers on 7/4/2022 on the project work for the design, implementation, operation and maintenance of Smart Park type parking lots for the assigned center at a value of 7,200,000 dinars for a period (430) days, and the direct order issued on 10/12/2019 shows the following:
1- The percentage of completed work reached (80%), while the elapsed period amounted to (231%), which led to a significant delay in completing the project despite the center’s commitment to disburse financial payments. Due to the contractor without delay at a rate of (76%).
2- The implementation period exceeded more than double the contractual period, and the approved time extensions amounted to (502) days, representing (116%) of the contractual period, so that the final delivery date was on 5/2/2022 instead of 12/15/2020, and it was not adhered to. The contractor completed the provision of the technical staff and the project was not completed.
3- The significant delay in implementing the project led to the loss of the benefit of supplying the Fund of the University of Jordan and the Diabetes Center with financial revenues according to the share of each party’s contribution to the capital in accordance with the terms of the investment agreement concluded between the two parties.